City of Pasadena – EVR Phase II Upgrades

Project: In accordance with a regulation change, this client looked to MJK to manage and perform EVR Phase II upgrades at four locations.

Challenge: With less than 21 days left before a state-mandated deadline, this municipality looked to MJK to provide a short turn around on this work at four fleet yard facilities. Despite the short turnaround needed, the industry was facing a shortage of the approved EVR systems needed for installation. Failure to meet the deadline would mean regulatory fines and penalties for this client.

MJK Solution: MJK assigned a team of dedicated individuals to focus on this project to insure the deadlines were met. We worked closely with the City to push permits through the permitting process and contacted our most valued suppliers, securing the necessary parts despite the shortage of availability. MJK was the proud recipient of special recognition from the City of Pasadena for a job well done.